Revenue Procedure 2012-50 allows sponsors of individually designed governmental plans to elect Cycle E (instead of Cycle C) as their second remedial amendment cycle.

Cycle E election
Sponsors can elect Cycle E as their second remedial amendment cycle by filing a determination letter application for their plan between February 1, 2015 and January 31, 2016, instead of the second Cycle C submission period (February 1, 2013 - January 31, 2014). Sponsors don’t need to notify the IRS of their intent to make this election.

Sponsors who elect Cycle E must:

  • amend their plans for all applicable items on the second Cycle E Cumulative List, and
  • timely adopt any interim amendments required for governmental plans during the second Cycles C and D.

Sponsors electing Cycle E as their second remedial amendment cycle will have their plans’:

  • subsequent remedial amendment cycles revert to Cycle C (for example, the plan’s third remedial amendment cycle will be the third Cycle C), and
  • second cycle determination letter expire at the end of the third Cycle C submission period (January 31, 2019).

Prior determination letter
Determination letters for individually designed governmental plans issued after the initial remedial amendment cycle expire on January 31, 2014 (at the end of the second Cycle C), even if the sponsor elected the first Cycle E as the plan’s initial cycle. However, the IRS will extend the expiration dates on these letters to January 31, 2016 (the end of second Cycle E), if the sponsor elects Cycle E as the plan’s second remedial amendment cycle.