| APPENDIX B |
| APPLICATION FOR DOE CERTIFICATION |
| REQUEST
FOR SUPPLEMENTAL APPLICATION INFORMATION FOR DOE |
| |
|
| Pursuant to Notice 2006-24 establishing
the Qualifying Advanced Coal Project Program, the Internal Revenue Service
(“IRS”) will allocate a credit under § 48A of the Internal
Revenue Code to a project only if, among other things, the IRS receives from
the Department of Energy (“DOE”) a certification of feasibility
and consistency with energy policy goals (“DOE certification”)
for the project. This DOE certification shall assure that the applications
selected meet the requirements of § 48A and the intent of §
48A to provide credits to projects that are both technically and economically
feasible.
|
| The IRS and DOE seek to certify applications
that demonstrate a high likelihood of being successfully implemented by the
applicants. To qualify, projects must be economically feasible and use the
appropriate clean coal technology.
|
| This request for submission of supplemental
application information:
|
| |
1. Describes the information to be provided by the applicant seeking
a DOE certification, and
|
| |
2. Lists the evaluation criteria, and Program Policy Factors to be
used by DOE in the evaluation of applications.
|
| In conducting this evaluation, the DOE
may utilize assistance and advice from qualified personnel from other Federal
agencies and/or non-conflicted contractors. DOE will obtain assurances in
advance from all evaluators that application information shall be kept confidential
and used only for evaluation purposes. DOE reserves the right to request
clarifications and/or supplemental information from some or all applicants
through written submissions and/or oral presentations.
|
| Notice is given that DOE may determine
whether or not to provide a DOE certification to the IRS at any time after
the application has been received, without further exchanges or discussions.
Therefore, all applicants are advised to submit their most complete and responsive
application.
|
| Applications will not be returned. |
| SUBMISSION INFORMATION FOR DOE CERTIFICATION
APPLICATION
|
| A. General |
| This request, together with the information
in sections 5.02, 7.01, and 7.02 of Notice 2006-24 includes all the information
needed to complete an application for DOE certification. All applications
shall be prepared in accordance with this request in order to provide a standard
basis for evaluation and to ensure that each application will be uniform as
to format and sequence.
|
| Each application should clearly demonstrate
the applicant’s capability, knowledge, and experience in regard to the
requirements described herein.
|
| Applicants should fully address the requirements
of Notice 2006-24 and this request and not rely
on the presumed background knowledge of reviewers. DOE may reject an application
that does not follow the instructions regarding the organization and content
of the application when the nature of the deviation and/or omission precludes
meaningful review of the application.
|
| B. Unnecessarily
Elaborate Applications |
| Unnecessarily elaborate brochures or other
presentations beyond those sufficient to present a complete and effective
application are not desired. Elaborate art work, graphics and pictures are
neither required nor encouraged.
|
| C. Application
Submission for DOE Certification |
| The application submission to DOE must
include the information and documentation required by sections 5.02, 7.01,
and 7.02 of Notice 2006-24.
|
| A project will not be considered in the
allocation round conducted in a calendar year unless the application for DOE
certification of the project is postmarked by June 30 of that calendar year.
Two paper copies and one electronic version on a floppy disc or a CD of the
Application must be submitted to:
|
| Melissa Robe National Energy Technology
Laboratory 3610 Collins Ferry Road Morgantown, WV 26507
|
| Note that under section 5 of Notice 2006-24,
one paper copy must be sent to the IRS as part of the application for IRS
certification. The project will not be considered in the allocation round
conducted in a calendar year unless the application is submitted to the IRS
by the date specified for that calendar year in section 4.02(8) of Notice
2006-24.
|
| THE INFORMATION
REQUIRED BY THIS REQUEST MUST BE SUBMITTED USING THE FORMAT AND THE HEADINGS
OF THE “PROJECT INFORMATION MEMORANDUM” AS DESCRIBED BELOW. |
| To aid in evaluation, applications shall
be clearly and concisely written and logically assembled. All pages of each
part shall be appropriately numbered and identified with the name of the applicant
and the date.
|
| The application, including the Project
Information Memorandum, MUST be formatted in one of the following software
applications:
|
| Microsoft Wordtm 2002
or later edition
|
| Microsoft Exceltm 2002
or later edition
|
| Adobe Acrobattm PDF
6.0 or later edition
|
| Financial models should be submitted using
the Exceltm spreadsheet and must include calculation
formulas and assumptions.
|
| The applicant is responsible for the integrity
and structure of the electronic files. The DOE will not be responsible for
reformatting, restructuring or converting any files submitted under this announcement.
|
| The Project Information Memorandum, excluding
Appendices, shall not exceed seventy-five (75) pages. Pages in
excess of the page limitation will not be considered for evaluation. All
text shall be typed, single spaced, using 12 point font, 1 inch margins, and
unreduced 8-1/2-inch by 11-inch pages. Illustrations and charts shall be
legible with all text in legible font. Pages shall be sequentially numbered.
Except as otherwise noted herein the page guidelines previously set forth
constitute a limitation on the total amount of material that may be submitted
for evaluation. No material may be incorporated in any application by reference
as a means to circumvent the page limitation.
|
| D. Form of Project
Information Memorandum |
| PROJECT INFORMATION MEMORANDUM |
| I. SUMMARY AND INTRODUCTION |
| |
-
Description of the Project
-
Financing and Ownership Structure
-
Describe the main parties to the project, including background, ownership
and related experience
-
Current Project Status and Schedule to Beginning of Construction
|
| II. TECHNOLOGY AND TECHNICAL INFORMATION |
| |
Provide a description of the proposed technology, including sufficient
supporting information (such as process flow diagrams, equipment descriptions,
information on each major process unit and the total plant, compositions of
major streams, and the technical plan for achieving the goals proposed for
the project) as would be needed to allow DOE to confirm that the technical
requirements of § 48A could, in principle, be met. Specifically
the applicant should:
|
| |
-
Provide evidence sufficient to demonstrate that the proposed technology
meets the definition of “Advanced Coal-Based Generation Technology,”
either as integrated gasification combined cycle (IGCC) technology, or other
advanced coal-based electric generation technology meeting the heat rate requirement
of 8530 Btu/kWh
-
The applicant must provide actual heat rate and heat rate corrected
to conditions specified in § 48A(f)(2)
-
For projects including existing units, the applicant must provide information
sufficient to justify that the proposed technology meets heat rate requirements
specified in § 48A(f)(3)
-
Provide evidence sufficient to ensure that the proposed project is designed
to meet the following performance requirements:
-
SO2 percent removal........99 percent
-
NOx emissions..................0.07 lbs / MMBTU
-
PM emissions....................0.015 lbs / MMBTU
-
Hg percent removal..........90 percent
-
Provide evidence sufficient to demonstrate that the project meets the
requirements for qualifying advanced coal projects as specified under § 48A(e)(1)
including:
-
Provide information and data, including examples of prior similar projects
completed by applicant, EPC contractor, and suppliers of major subsystems
or equipment which support the capabilities of the applicant to construct
and operate the facility.
-
Include the project status and relevant information from ongoing engineering
activities. Also include in an appendix any engineering report or reports
used by the applicant to develop the project and to estimate costs and operating
performance.
|
| III. PRIORITY FOR INTEGRATED GASIFICATION
COMBINED CYCLE PROJECTS
|
| |
For IGCC Projects, the applicant must submit information sufficient
for categorization and prioritization of projects for certification, including:
|
| |
-
Identification of the primary feedstock (as defined in section 5.02(5)
of Notice 2006-24), and all other feedstocks.
-
If applicable, evidence demonstrating that the project will be capable
of adding components that can capture, separate and permanently sequester
greenhouse gases.
-
A plan showing how project by-products will be marketed and utilized.
-
Other benefits, if any.
|
| IV. SITE CONTROL AND OWNERSHIP |
| |
-
Provide evidence that the applicant owns or controls a site in the United
States of sufficient size to allow the proposed project to be constructed
and operated on a long-term basis.
-
Describe the current infrastructure at the site available to meet the
needs of the project.
-
Provide information supporting applicant’s conclusion that the
proposed site can fully meet all environmental, coal supply, water supply,
transmission interconnect, and public policy requirements.
|
| V. UTILIZATION OF PROJECT OUTPUT |
| |
-
A projection of the anticipated costs of electricity and other marketable
by-products produced by the plant.
-
Provide evidence that a majority of the output of the plant is reasonably
expected to be acquired or utilized.
-
Describe any energy sales arrangements that exist or that may be contemplated, e.g.,
Power Purchase Agreement or Energy Sales Agreement, and summaries of their
key terms and conditions.
-
Include as an appendix any independent Energy Price Market Study that
has been done in connection with this project, or if no independent market
study has been completed, provide a copy of the applicant-prepared market
study.
-
Identify and describe any firm arrangements to sell non-power output,
and provide any evidence of such arrangements. If the project produces a
product in addition to power, include as an appendix any related market study
of price and volume of sales expected for that product.
|
| VI. PROJECT ECONOMICS |
| |
Describe the project economics and provide satisfactory evidence of
economic feasibility as demonstrated through the financial forecast and the
underlying project assumptions.
|
| |
Discuss the market potential for the proposed technology beyond the
project proposed by the applicant.
|
| |
Show calculation of the amount of tax credit applied for based on allowable
cost.
|
| VII. PROJECT DEVELOPMENT AND FINANCIAL
PLAN
|
| |
Provide the total project budget and major plant costs, e.g.,
development, operating, capital, construction, and financing costs. Describe
the overall approach to project development and financing sufficient to demonstrate
project viability. Provide a complete explanation of the source and amount
of project equity. Provide a complete explanation of the source and amount
of project debt. Provide the audited financial statements for the applicant
for the most recently ended three fiscal years, and the unaudited quarterly
interim financial statements for the current fiscal year.
|
| |
For internally financed projects, provide evidence that the applicant
has sufficient assets to fund the project with its own resources. Identify
any internal approvals required to commit such assets. Include in an appendix
copies of any board resolution or other approval authorizing the applicant
to commit funds and proceed with the project.
|
| |
For projects financed through debt instruments either unsecured or
secured by assets other than the project, provide evidence that the applicant
has sufficient creditworthiness to obtain such financing along with a discussion
of the status of such instruments. Identify any internal approvals required
to commit the applicant to pursue such financing. Include in an appendix,
copies of any board resolution or other approval authorizing the applicant
to commit to such financing.
|
| |
For projects financed through investor equity contributions, discuss
the source and status of each contribution. Discuss each investor’s
financial capability to meet its commitments. Include in an appendix, copies
of any executed investment agreements.
|
| |
If financing through a public offering or private placement of either
debt or equity is planned for the project, provide the expected debt rating
for the issue and an explanation of applicant’s justification for the
rating. Describe the status of any discussions with prospective investment
bankers or other financial advisors.
|
| |
For projects employing nonrecourse debt financing, provide a complete
discussion of the approach to, and status of, such financing.
|
| |
In an appendix, provide (1) an Excel based financial model of the project,
with formulas, so that review of the model calculations and assumptions may
be facilitated; provide pro-forma project financial,
economic, capital cost, and operating assumptions, including detail of all
project capital costs, development costs, interest during construction, transmission
interconnection costs, other operating expenses, and all other costs and expenses,
and (2) a report of an independent financial analyst in accordance with the
instructions in Section G of this Appendix B.
|
| VIII. PROJECT CONTRACT STRUCTURE |
| |
Describe the current status of each of the agreements set forth below.
Include as an appendix copies of the contracts or summaries of the key provisions
of each of the following agreements:
|
| |
-
Power Purchase Agreement (if not fully explained in Section IV)
-
Coal Supply: describe the source and price of coal supply for the project.
Include as an appendix any studies of coal supply price and amount that have
been prepared. Include a summary of the coal supply contract and a copy of
the contract.
-
Coal transportation: explain the arrangements for transporting coal,
including costs.
-
Operations & Maintenance Agreement: include a summary of the terms
and conditions of the contract and a copy of the contract.
-
Shareholders Agreement: summarize key terms and include the agreement
as an appendix.
-
Engineering, Procurement and Construction Agreement: describe the key
terms of the existing or expected EPC contract arrangement, including firm
price, liquidated damages, hold-backs, performance guarantees, etc.
-
Water Supply Agreement: confirm the amount, source, and cost of water
supply.
-
Transmission interconnection agreement: explain the requirements to
connect to the system and the current status of negotiations in this respect.
|
| IX. PERMITS INCLUDING EVIRONMENTAL AUTHORIZATIONS |
| |
-
Provide a complete list of all federal, state, and local permits, including
environmental authorizations or reviews, necessary to commence construction
of the project.
-
Explain what actions have been taken to date to satisfy the required
authorizations and reviews, and the status of each.
-
Provide a description of the applicant’s plan to obtain and complete
all necessary permits, and environmental authorizations and reviews.
|
| X. STEAM TURBINE PURCHASE |
| |
-
If applicant plans to purchase a steam turbine or turbines for the project,
indicate the prospective vendors for the turbine and explain the current status
of purchase negotiations, and provide a timeline for negotiation and purchase
with expected purchase date.
|
| XI. PROJECT SCHEDULE |
| |
-
Provide an overall project schedule which includes technical, business,
financial, permitting and other factors to substantiate that the project will
meet the 2 year project certification and 5 year placed-in-service requirement.
|
| APPENDICES |
| |
-
Independent Financial Report.
-
Copy of internal or external engineering reports.
-
Copy of site plan, together with evidence that applicant owns or controls
a site. Examples of evidence would include a deed, or an executed contract
to purchase or lease the site.
-
Information supporting applicant’s conclusion that the site is
fully acceptable as the project site with respect to environment, coal supply,
water supply, transmission interconnect, and public policy reasons.
-
Power Purchase or Energy Sales Agreement.
-
Energy Market Study.
-
Market Study for non-power output.
-
Financial Model of project.
-
Audited financial statements for the applicant for the most recently
ended three fiscal years, and the unaudited quarterly interim financial statements
for the current fiscal year.
-
For each project contract, if no contract currently exists, provide
a summary of the expected terms and conditions.
-
List of all federal, state, and local permits, including environmental
authorizations or reviews, necessary to commence construction.
-
If an appendix listed above is not provided, include in its place a
complete explanation of the reasons for the omission.
|
| E. Evaluation Criteria: |
| Advanced coal projects: will be evaluated
on whether they meet all the requirements of § 48A.
|
| Technical: will be evaluated on whether
the applicant has demonstrated the capability to accomplish the technical
objectives.
|
| Site: will be evaluated on the basis
that the site requirement for ownership or control has been met, and that
the site is suitable for the proposed project.
|
| Economic: will be evaluated on whether
the project has demonstrated economic feasibility, taking into consideration
the submitted financial and project development and structural information
and financial plan.
|
| Schedule: will be evaluated on the applicant’s
ability to meet the 2 year project certification and the 5 year placed-in-service
requirement.
|
| F. Program Policy
Factors to be used by DOE in the evaluation of applications and a description
of how they will be applied. |
| These factors, while not indicators of
the applicant’s merit, e.g., technical excellence,
cost, applicant’s ability, etc., may be essential to the process of
selecting the application(s) that, individually or collectively, will best
achieve the objectives of the authorizing legislation. Such factors are often
beyond the control of the applicant. Applicants should recognize that some
very good applications may not receive selection for certification because
they do not fit within a mix of projects and technologies that maximize the
probability of achieving the overall objective of deployment of advanced coal-based
generation technology. Therefore, the following Program Policy Factors may
be used individually or collectively by DOE following application of evaluation
criteria to determine which of the applications shall receive certification
by DOE.
|
| |
-
Diversity of technology approaches and methods
-
Geographic distribution of potential markets
-
Presentation of unique environmental, economic, or performance benefits
|
| G. Instructions
for independent financial reports |
| The applicant shall provide an independent
report by a qualified Independent Financial Analyst (such as a bank, investment
bank, or other independent financial advisory firm). In the report, the Independent
Financial Analyst shall describe qualifications and experience that establish
the Analyst’s competence to evaluate project financing for projects
similar in scope and size to the Applicant’s project. The Independent
Financial Analyst shall provide a thorough, independent review of the Applicant’s
approach to project financing. The report shall include the opinion of the
Independent Financial Analyst as to the Applicant’s likelihood to achieve
financial closure in accordance with the Applicant’s financing plan.
|
| Required Certification
by Independent Financial Analyst: |
| The report shall
be certified by the Independent Financial Analyst, who shall (a) acknowledge
that the report has been prepared for submission to the Department of Energy
as a part of an application by applicant for an investment credit, and (b)
certify that the Independent Financial Analyst has no obligation to the applicant
and has acted to the best of its ability as an independent expert. |
| At a minimum, the
Independent Financial Analyst shall: |
| |
-
Review the financial model.
-
Review the project financial assumptions, including economic, capital
costs, operating assumptions, and all project development costs.
-
Review the financial calculations, including rates of return and coverage
ratios.
-
Confirm the calculation of the amount of the tax credit applied for.
-
Review the project development cost budget.
-
Review and comment on the source of funding and evidence of funding.
-
Review and comment on project debt and equity sources.
-
Confirm that the application includes the required financial reports
and debt ratings.
-
Describe and comment on the capabilities of the applicant to provide
the required financing for the project, and the likelihood of obtaining financing
from a source other than the applicant, if such financing is required by the
project.
|