Independent Government Cost Estimate (IGCE)

From the sub-tasks identified in your draft SOW, each customer is required to develop an IGCE based on the number of hours (Level of Effort) in each labor category, see Section C.7 of the contract that you anticipate to complete your task(s).

The Requirements Development Team is available to assist you with developing the IGCE.
 
A well-constructed IGCE allows the customer to inform their management of the amount of estimated hours and funding to support their requirement.